Multi-year works plan in a co-ownership: obligations, vote, works fund and grants

Published 16 November 2026 · Reading time: 6 min

In short: a building wholly or partly used for housing must, fifteen years after completion, have a draft multi-year works plan (PPT) drawn up for ten years, updated every ten years. Its adoption is voted by a majority of all co-owners' votes. The works fund receives each year at least 5% of the forecast budget (or 2.5% of the adopted plan's works). Aids exist to finance works on common parts.

1. What the PPT contains

According to the INC (page checked on 26 June 2026), the draft PPT rests on an analysis of the state of the building and equipment, on the collective energy performance diagnostic and, if there is one, on the global technical diagnostic (DTG). It includes the list of necessary works, the expected performance level, a rough cost estimate with priorities, and a schedule for works to plan within ten years. It is drawn up by a qualified professional independent of the managing agent (unless the meeting authorises otherwise) and of contractors. If a DTG concludes that no works are needed within ten years, the co-ownership is exempt.

2. Who is concerned and when

The obligation arises after fifteen years from completion of the construction works, for buildings wholly or partly used for housing. According to our secondary sources, the roll-out by co-ownership size has been complete since 1 January 2025 (see our article on the collective DPE and the PPT, in French). The administrative authority can ask for the adopted plan; if it is not sent within a month, or if it clearly omits necessary works, it can draw it up or update it at the co-ownership's expense.

3. How the vote works

4. The works fund

According to the INC (page checked on 11 February 2026), the annual contribution cannot be below 5% of the forecast budget, nor, when a PPT is adopted, below 2.5% of the works it plans. The fund has been compulsory since 1 January 2023 ten years after completion (five years before), for all co-ownerships since 1 January 2025. The sums are definitively acquired by the co-ownership: they are not refunded to the seller of a unit.

5. Aids to finance the works

Sources

Frequently asked questions

From when is a PPT needed?

After fifteen years from completion of construction, for a building wholly or partly used for housing.

What if the meeting refuses to adopt the PPT?

The draft stays a draft; the meeting must nevertheless decide each time it approves the accounts. The administrative authority can step in if the plan is requested and not supplied.

What is the minimum works fund?

5% of the forecast budget, or 2.5% of the adopted PPT's works if that amount is higher.

Are the aids paid to each co-owner?

MaPrimeRénov' Copropriété is paid to the co-ownership, then shared by shares; additional individual bonuses depend on income.

Look up your building's record

Construction period, units, managing agent, heating and surroundings: public data from the national co-ownership register.

Search a co-ownership

Informational article based on INC pages (26 June 2026 and 11 February 2026) and service-public.gouv.fr. The conditions and rates of MaPrimeRénov' Copropriété come from secondary sources and are not confirmed on the Anah site: check them before voting works. This is not legal advice. Source titles are given in French.